STATEMENT SHOWING PROGRESS OF WORKS UNDER M.P.'S LOCAL AREA DEVELOPMENT SCHEME (M.P.-WISE AND YEARWISE)
 FOR THE PERIOD FROM 1999-2000

Name of the M.P. : Shri. P.R. Kyndiah M.P. (LS)
-----------------------------------------------------------------------------------------------------------------------------------------------------
 SL |  Name of Block   |Year |      Name of the Scheme    |Amount  Approved/|     Amount      |   Physical    |Date/Expected| Reasons for delay
 No.|                  |     |                            |Recommmended  by |    utilised     |Status/Position|  Date  of   | in  Completion/Remarks
    |                  |     |                            |    the M.P.     |   till date     | of the Scheme |  Completion |
    |                  |     |                            |Sanctioned with  |                 |               |             |
    |                  |     |                            |     Date        |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  1 |     Mylliem      |1999-| 1. Cont. of footpath at    | Rs.   50,000 /- | Rs.   50,500 /- | Completed     |             |         70 %
    |   Development    |2000.|Nongkseh.                   |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  2 |     Mylliem      |1999-| 2. Const. of playground at | Rs.   30,000 /- | Rs.   30,000 /- | Completed     |             |
    |   Development    |2000.|Umiew village Pomlakrai     |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  3 |     Mylliem      |1999-| 3. Const. of footpath at   | Rs.   50,000 /- | Rs.   50,000 /- | Completed     |             |
    |   Development    |2000.|Umlyngka village.           |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  4 |     Mylliem      |1999-| 4. Const. of Govt. L.P     | Rs. 7,50,000 /- | Rs. 7,50,000 /- | Completed     |             |
    |   Development    |2000.|School at Nongumlong        |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  5 |     Mylliem      |1999-| 5. Const. of compound wall | Rs.   30,000 /- | Rs.   22,500 /- | Completed     |             |
    |   Development    |2000.|at Deisngi L.P School       |     10-5-2001   |                 |               |             |
    |                  |     |Mawkriah Mawkohnguh.        |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  6 |     Mylliem      |1999-| 6. Const. of Community Hall| Rs.   50,000 /- | Rs.   37,500 /- | Completed     |             |
    |   Development    |2000.|at Kreit Nongshiliang.      |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  7 |     Mylliem      |1999-| 7. Const. of playground at | Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    |   Development    |2000.|Lumkshaid  Lower Mawprem    |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  8 |     Mylliem      |1999-| 8. Const. of creamation    | Rs. 2,00,000 /- | Rs. 2,00,000 /- | Completed     |             |
    |   Development    |2000.|ground at Jaiaw.            |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
  9 |     Mylliem      |1999-| 9. Const. of playground at | Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    |   Development    |2000.|Mawtharia.                  |     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 10 |     Mylliem      |1999-|10. Const. of Mini Stadium  | Rs. 2,00,000 /- | Rs. 1,50,000 /- | In Progress   |             |         75 %
    |   Development    |2000.|cum Auditorium Complex at   |     10-5-2001   |                 |               |             |
    |                  |     |Lumparing.                  |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 11 |     Mylliem      |1999-|11. Purchase of Ambulance   | Rs. 2,71,000 /- | Rs. 2,71,000 /- | Completed     |             |
    |   Development    |2000.|for Meghalaya Gurkha Ex-    |     10-5-2001   |                 |               |             |
    |                  |     |Servicemen Union, Shg-2.    |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 12 |     Mylliem      |1999-|12. Const. of Community Hall| Rs. 1,00,000 /- | Rs.   75,000 /- | Completed     |             |
    |   Development    |2000.|at Mawlai Mawkynroh Umshing.|     10-5-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 13 |     Mylliem      |1999-|13. Const. of wlll fencing  | Rs. 2,00,000 /- | Rs. 2,00,000 /- | Completed     |             |
    |   Development    |2000.|at St.Mary College Shillong |     10-5-2001   |                 |               |             |
    |                  |     |(for women)                 |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 14 |     Mylliem      |1999-|14. Const. of School buil-  | Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    |   Development    |2000.|ding of Bangalee Girls High |     10-5-2001   |                 |               |             |
    |                  |     |School Upper New Colony.    |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 15 |     Mylliem      |1999-|15. Purchase of Computer for| Rs. 2,86,334 /- | Rs. 2,86,334 /- | Completed     |             |
    |   Development    |2000.|Lakreh Memorial School      |     10-5-2001   |                 |               |             |
    |                  |     |Umsohsun, Shillong.         |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 16 |     Mylliem      |1999-|16. Cont. of Mawlai Pres.   | Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    |   Development    |2000.|College Mawlai Iewrynghep   |     6-8-2001    |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 17 |     Mylliem      |1999-|17. Const. of building of   | Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    |   Development    |2000.|Synod High School Mission   |     6-8-2001    |                 |               |             |
    |                  |     |Compound, Shillong.         |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 18 |     Mylliem      |1999-|18. Extension of YMCA       | Rs. 1,50,000 /- | Rs. 1,50,000 /- | Completed     |             |
    |   Development    |2000.|building(3rd floor) Mawkhar |     6-8-2001    |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 19 |     Mylliem      |1999-|19. Const. of footpath at   | Rs. 1,50,000 /- | Rs. 1,12,500 /- | Completed     |             |
    |   Development    |2000.|Upper Shillong.             |     6-8-2001    |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 20 |     Mylliem      |1999-|20. Const. of Laitkor Upper | Rs. 1,00,000 /- | Rs. 1,00,000/-  | Completed     |             |
    |   Development    |2000.|Primary School Bulding.     |     6-8-2001    |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 21 |     Mylliem      |1999-|21. Const. of Vocation      | Rs. 1,00,000 /- | Rs. 1,00,000/-  | Completed     |             |
    |   Development    |2000.|Training Institute, Laban   |     6-8-2001    |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 22 |     Mylliem      |1999-|22. (a) Extension of        | Rs. 2,50,000 /- | Rs. 2,50,000 /- | Completed     |             |
    |   Development    |2000.|Rangbihbih L.P. School,     |     6-8-2001    |                 |               |             |
    |                  |     |Pomlakrai.                  |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
    |                  |     |    (b) Extension of        | Rs. 2,50,000/-  | Rs. 2,50,000 /- | Completed     |             |
    |                  |     |St. Mary's L.P. School,     |     6-8-2001    |                 |               |             |
    |                  |     |Mylliem, 10 Mer.            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 23 |     Mylliem      |1999-|23. Const. of fencing and   | Rs.   50,000 /- | Rs.   50,500 /- | Completed     |             |
    |   Development    |2000.|grill around of Community   |     6-8-2001    |                 |               |             |
    |                  |     |Hall at Nongsohphoh and     |                 |                 |               |             |
    |                  |     |Naspatighari.               |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 24 |     Mylliem      |1999-|24. Construction of footpath| Rs.   30,000 /- | Rs.   22,000 /- |               |             |
    |   Development    |2000.|from Presbyterian Church    |     6-8-2001    |                 |   -do-        |             |
    |                  |     |burial ground, Mawpynthih.  |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 25 |     Mylliem      |1999-|25. Construction of footpath| Rs.   50,000 /- | Rs.   50,000 /- | Completed     |             |
    |   Development    |2000.|from PWD Road to Umlidoh.   |   27-11-2001    |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 26 |     Mylliem      |1999-|26. Construction of         | Rs.   50,000 /- | Rs.   50,000 /- | Completed     |             |
    |   Development    |2000.|Community Hall at           |   27-11-2001    |                 |               |             |
    |                  |     |Nongsawing.                 |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 27 |     Mylliem      |1999-|27. Construction of School  | Rs. 4,00,000 /- | Rs. 4,00,000 /- | Completed     |             |
    |   Development    |2000.|building of Umiew           |   21-12-2001    |                 |               |             |
    |                  |     |Presbyterian L.P. School,   |                 |                 |               |             |
    |                  |     |Umiew, Pomlakrai.           |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 28 |     Mylliem      |1999-|28. Construction of         | Rs.   30,000 /- | Rs.   30,000/-  | Completed     |             | 
    |   Development    |2000.|Cemented Wall and Lanes at  |    23.11.2002   |                 |               |             |  
    |                  |     |Mawtharia, Pomlakrai.       |                 |                 |               |             | 
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 29 |     Mylliem      |1999-|29. Construction of         | Rs. 1,00,000 /- | Rs. 1,00,000/-  | Completed     |             | 
    |   Development    |2000.|Vocational Training Centre  |    9.1.2003     |                 |               |             | 
    |                  |     |at Mawkhar.                 |                 |                 |               |             | 
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 30 |   Mylliem        |1999-|20. Construction of Multi-  | Rs. 5,00,000 /- | Rs. 5,00,000 /- | Completed     |             | 
    |   C  & R D       |2000 |Purpose building at         |     12-4-2002   |                 |               |             | 
    |                  |     |St. Francis D. Assissi      |                 |                 |               |             | 
    |                  |     |School, Mawkasiang.         |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 31 | Mawryngkneng     |1999-| 1. Const. of School        | Rs. 1,00,000 /- | Rs.   75,000 /- | Completed     |             |
    | Dev. Block       |2000.|building of Tynring Upp.    |     10-5-2001   |                 |               |             |
    |                  |     |Primary School              |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 32 | Mawryngkneng     |1999-| 2. Const. of Culvert and   | Rs. 5,00,000 /- | Rs.   37,500 /- | Completed     |             |
    | Dev. Block       |2000.|Retaining wall at Kharbuli  |     10-5-2001   |                 |               |             |
    |                  |     |                            |      4.3.2001   |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 33 | Mawryngkneng     |1999-| 3. Const. of road at Pata  | Rs.   20,000 /- | Rs. 15,000 /-   |               |             |
    | Dev. Block       |2000.|Mawbiar.                    |      6-8-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 34 | Mawryngkneng     |1999-| 4. Const. of RCLP School   | Rs.   20,000 /- | Rs.   15,000 /- | In Progress   |             |
    | Dev. Block       |2000.|at Thadan.                  |      6-8-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 35 | Mawryngkneng     |1999-| 5. Const. of road at Madan | Rs. 1,00,000 /- | Rs.   75,000 /- | In Progress   |             |
    | Dev. Block       |2000.|Center Kharbuli             |      6-8-2001   |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 36 | Mawryngkneng     |1999-| 6. Const. of Dymmiew Pres- | Rs. 1,00,000 /- | Rs.   75,000 /- | Completed     |             |
    | Dev. Block       |2000.|byterian Upp. School        |      6-8-2001   |                 |               |             |
    |                  |     |Umphyrnai                   |      9.7.2001   |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 37 | Mawryngkneng     |1999-| 7. Purchase of Ambulance   | Rs. 2,71,000 /- | Rs. 2,71,000 /- | Completed     |             |
    | Dev. Block       |2000.|for Nongkrem Social and     |      6-8-2001   |                 |               |             |
    |                  |     |Voluntary Organisation      |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 38 | Mawryngkneng     |1999-| 8. Const. of Ing Balieh    | Rs. 6,00,000 /- | Rs. 4,50,000 /- | In Progress   |             |
    | Dev. Block       |2000.|of Warbah Socil Cultural    |      6-8-2001   |                 |               |             |
    |                  |     |Club Nongkrem               |      9.7.2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 39 | Mawryngkneng     |1999-| 9. Const. of playfield     | Rs. 5,00,000 /- | Rs. 3,75,000 /- | In Progress   |             |
    | Dev. Block       |2000.|at Laitkreh                 |      6-8-2001   |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 40 |    Mawryngkneng  |1999-|10. Const. of School buil-  | Rs. 7,00,000 /- | Rs. 5,25,000 /- | In Progress   |             |
    |   Development    |2000 |ding of Nongkrem Presbyte-  |      6-8-2001   |                 |               |             |
    |      Block       |     |rian School, Mawpynthaw     |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 41 |    Mawryngkneng  |1999-|11. Const. of retaining wall| Rs. 5,00,000 /- | Rs. 3,75,000 /- | In Progress   |             |
    |   Development    |2000 |fencing,filling etc at foot-|      6-8-2001   |                 |               |             |
    |      Block       |     |ball ground mawdija         |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 42 |    Mawryngkneng  |1999-|12. Const. of basket ball   | Rs. 5,00,000 /- | Rs. 3,75,000 /- | In Progress   |             |
    |   Development    |2000 |court with galery at Green  |      6-8-2001   |                 |               |             |
    |      Block       |     |High School, Sohryngkham    |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 43 |    Mawryngkneng  |1999-|13. Levelling the School    | Rs. 5,00,000 /- | Rs. 3,75,000 /- | In Progress   |             |
    |   Development    |2000 |ground at St.Francis School |      6-8-2001   |                 |               |             |
    |      Block       |     |Smit.                       |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 44 |    Mawryngkneng  |1999-|14. Construction of Check   | Rs. 2,00,000 /- | Rs. 1,50,000 /- | In Progress   |             | 
    |   Development    |2000 |Dam Irrigation Project at   |      6-8-2001   |                 |               |             |
    |      Block       |     |Dymmiew Jynru, Thadan.      |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 45 |    Mawryngkneng  |1999-|15. Const. of Farmer's      | Rs. 5,00,000 /- | Rs. 3,75,000 /- |               |             | 
    |   Development    |2000 |godown cum-Community Hall   |      6-8-2001   |                 |               |             | 
    |      Block       |     |Nongkrem.                   |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 46 | Mawryngkneng     |1999-|16. Construction of building| Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    | Dev. Block       |2000.|of R.S. Lyngdoh Training    |     27-11-2001  |                 |               |             |
    |                  |     |Institution, Smit.          |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 47 | Mawryngkneng     |1999-|17. Construction of School  | Rs.   50,000 /- | Rs.   50,000 /- | Completed     |             | 
    | Dev. Block       |2000.|building at Mawbiar RCLP    |     13-3-2002   |                 |               |             | 
    |                  |     |School.                     |                 |                 |               |             |  
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 48 | Mawryngkneng     |1999-|18. Construction of School  | Rs.   50,000 /- | Rs.   50,000 /- | Completed     |             | 
    | Dev. Block       |2000.|building at Mawpyrshong     |      13-3-2002  |                 |               |             | 
    |                  |     |RCLP School.                |                 |                 |               |             | 
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 49 |    Mawryngkneng  |1999-|19. Construction of         | Rs. 1,25,000 /- | Rs. 1,25,000 /- | Completed     |             |
    |   Development    |2000 |Unitarian LP                |     12-4-2002   |                 |               |             |
    |      Block       |     |School, Nongkrem.           |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 50 |    Mawryngkneng  |1999-|21. Construction of Boiler  | Rs. 3,20,000 /- | Rs. 3,00,000 /- | Completed     |             |
    |   Development    |2000 |Dustbin, Latrine Urinals at |     13-3-2002   |                 |               |             |
    |      Block       |     |Smit Market.                |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 51 |    Mawryngkneng  |1999-|22. Construction of Washing | Rs. 1,00,000 /- | Rs.  75,000/-   | In progress   |             | 
    |   Development    |2000 |places at River Umiew, Smit |      9.1.2003   |                 |               |     60%     | 
    |      Block       |     |Village.                    |                 |                 |               |             | 
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 52 | Shella Bholganj  |1999-| 1. Const. of Hall Cum-     | Rs.   50,000 /- | Rs.   37,500 /- | Completed     |             |
    | Dev. Block       |2000 |office building of Synjuk   |      10-5-2001  |                 |               |             |
    |                  |     |Kynthei Sohra               |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 53 | Shella Bholganj  |1999-| 2. Const. of School        | Rs.   75,000 /- | Rs.   56,250 /- |               |             |
    | Dev. Block       |2000 |building Robasing Singh     |       10-5-2001 |                 |  -do-         |             |
    |                  |     |Syiem LP&ME School Mawkliaw |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 54 | Shella Bholganj  |1999-| 3. Const. of Dispensary    | Rs. 1,00,000 /- | Rs.  75,000 /-  |               |             |
    | Dev. Block       |2000 |at Mawlong                  |      10-5-2001  |                 |  -do-         |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 55 | Shella Bholganj  |1999-| 4. Const. of play ground   | Rs.   50,000 /- | Rs.   75,000 /- |  -do-         |             |
    | Dev. Block       |2000 |at Nongduh                  |       6-8-2001  |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 56 | Shella Bholganj  |1999-| 5. Const. of Footpath at   | Rs.   50,000 /- | Rs.   50,500 /- | Completed     |             |
    | Dev. Block       |2000 |Sder, Hima Sohra.           |      12-4-2002  |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 57 |   Mawkynrew      |1999-| 1. Construction of         | Rs.   20,000 /- | Rs.   15,000 /- | Completed     |             |
    |  Development     |2000.|Community Hall at           |     10-5-2001   |                 |               |             |
    |     Block        |     |Khlieh Shnong, Khapmaw.     |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 58 |   Mawkynrew      |1999-| 2. Construction of School  | Rs.   20,000 /- | Rs.   15,000 /- | Completed     |             |
    |  Development     |2000.|building of Presbyterian    |     10-5-2001   |                 |               |             |
    |     Block        |     |Lower Primary School,       |                 |                 |               |             |
    |                  |     |Umtangpiar, Khraang.        |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 59 |   Mawkynrew      |1999-| 3. Construction of Footpath| Rs.   20,000 /- | Rs.   15,000 /- | Completed     |             |
    |  Development     |2000.|at New Nongryngkoh.         |     10-5-2001   |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 60 |   Mawkynrew      |1999-| 4. Construction of Football| Rs. 5,00,000 /- | Rs. 3,75,000 /- | Completed     |             |
    |  Development     |2000.|Ground at Rapleng.          |     10-5-2001   |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 61 |   Mawkynrew      |1999-| 5. Construction of Footpath| Rs.   30,000 /- | Rs.   22,500 /- | Completed     |             |
    |  Development     |2000.|Ground at Jongksha.         |     10-5-2001   |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 62 |   Mawkynrew      |1999-| 6. Contruction of Laitlum  | Rs.   50,000 /- | Rs.   50,500 /- | Completed     |             |
    |  Development     |2000.|Presbyterian L.P. School.   |     6-8-2001    |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 63 |   Mawkynrew      |1999-| 7. Extension of School     | Rs. 5,00,000 /- | Rs. 3,75,000 /- | Completed     |             |Final payment yet to be 
    |  Development     |2000.|building at Thangsning      |     6-8-2001    |                 |               |             |made
    |     Block        |     |Presbyterian Upper Primary  |                 |                 |               |             |
    |                  |     |School.                     |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 64 |   Mawkynrew      |1999-| 8. Construction of Footpath| Rs.   30,000 /- | Rs.   30,500 /- | Completed     |             |
    |  Development     |2000.|from Rangphlang to          |     6-8-2001    |                 |               |             |
    |     Block        |     |Laitkyrhong.                |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 65 |   Mawkynrew      |1999-| 9. Construction of footpath| Rs.   50,000 /- | Rs.   50,000 /- | Completed     |             |
    |  Development     |2000.|at Rasong Village.          |   27.11.2001    |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 66 |   Mawkynrew      |1999-|10. Construction of Football| Rs.   30,000 /- | Rs.   30,000 /- | Completed     |             |
    |  Development     |2000.|Ground at Namlang.          |   27.11.2001    |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 67 |   Mawkynrew      |1999-|11. Construction of footpath| Rs. 3,00,000 /- | Rs. 3,00,000 /- | Completed     |             |
    |  Development     |2000.|at Umkhoi.                  |   27.11.2001    |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 68 |   Mawkynrew      |1999-|12. Construction of Footpath| Rs.   20,000 /- | Rs.   20,000 /- | Completed     |             |
    |  Development     |2000.|Ground at Mawlali, Khyrim   |   21.12.2001    |                 |               |             |
    |     Block        |     |Syiemship.                  |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 69 |   Mawkynrew      |1999-|13. Construction of Road at | Rs. 1,00,000 /- | Rs. 1,00,000 /- | Completed     |             |
    |  Development     |2000.|Nohron.                     |   21.12.2001    |                 |               |             |
    |     Block        |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 70 |   Mawkynrew      |1999-|14. Construction of         | Rs.    9,900 /- | Rs.    9,900 /- | Completed     |             |
    |  Development     |2000.|Retaining and Guard Wall at |   16.08.2002    |                 |               |             |
    |     Block        |     |Lyngdumpoh, Raid Mawlat,    |                 |                 |               |             |
    |                  |     |Khyrim Syiemship.           |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 71 |   Mawkynrew      |1999-|15. Construction of RCLP    | Rs.   20,000 /- | Rs.             |               |             | Not Sanction pending
    |  Development     |2000.|School at Wahlakhiat.       |                 |                 |               |             | submission of plan
    |     Block        |     |                            |                 |                 |               |             | and estimate and
    |                  |     |                            |                 |                 |               |             | execution of agreement.
-----------------------------------------------------------------------------------------------------------------------------------------------------
 72 |   Mawkynrew      |1999-|16. Construction of RCLP    | Rs.   20,000 /- | Rs.  15,000 /-  | Yet to start  |             | 
    |  Development     |2000.|School at Syniasya.         |     26.9.2003   |                 |               |             | 
    |     Block        |     |                            |                 |                 |               |             | 
    |                  |     |                            |                 |                 |               |             | 
-----------------------------------------------------------------------------------------------------------------------------------------------------
 73 |     Pynursla     |1999-| 1. Construction of         | Rs. 2,00,000 /- | Rs. 2,00,000 /- | Completed     |             |
    |    Development   |2000.|Community Hall at Nongshken.|     6-8-2001    |                 |               |             |
    |       Block      |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 74 |     Pynursla     |1999-| 1. Construction of footpath| Rs.   40,000 /- | Rs.   40,000 /- |   -do-        |             |
    |    Development   |2000.|at Nongmadan, (Mawpran).    |   21-12-2001    |                 |               |             |
    |       Block      |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 75 |    Mawphlang     |1999-| 1. Construction of         | Rs.   50,000 /- | Rs.   50,000 /- |   -do-        |             | 
    |   Development    |2000 |Footbridge at Wahumsohiong. |    10.5.2001    |                 |               |             |
    |      Block       |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 76 |    Mawphlang     |1999-| 2. Construction of         | Rs. 1,50,000 /- | Rs. 1,50,500 /- |   -do-        |             | 
    |   Development    |2000 |Playground at Hynniew       |     6.8.2001    |                 |               |             |
    |      Block       |     |Kyntoit Upper Primary       |                 |                 |               |             |
    |                  |     |School, Sohpian.            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 77 |    Mawphlang     |1999-| 3. Construction of Football| Rs. 2,50,000 /- | Rs. 2,50,000 /- | Completed     |             |
    |   Development    |2000 |Ground at Kynroh Nonglyer.  |     6.8.2001    |                 |               |             |
    |      Block       |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 78 |    Mawphlang     |1999-| 4. Construction of football| Rs.   80,000 /- | Rs.   60,000 /- | In Progress   |             |
    |   Development    |2000 |ground for Khyndai Kyntoit  |      17-5-2002  |                 |               |             |
    |      Block       |     |Wahlang.                    |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 79 |  Khatar Shnong   |1999-| 1. Construction of Road    | Rs.   50,000 /- | Rs.   50,500 /- | completed     |             |
    |     Laitkroh     |2000 |from Laitkynsew to Umthli   |                 |                 |               |             |
    |Development Block |     |Village, Langkyrdem.        |    6.8.2001     |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 80 |  Khatar Shnong   |1999-| 2. Extension of Raid       | Rs. 1,00,000 /- | Rs. 1,00,000 /- |   -do-        |             |
    |     Laitkroh     |2000 |Nongkynrih High School.     |    6.8.2001     |                 |               |             |
    |Development Block |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 81 |    Mawsynram     |1999-| 1. Construction of         | Rs.   35,000 /- | Rs.   35,250 /- |   -do-        |             |
    |   Development    |2000 |Community Hall at Jyllep    |                 |                 |               |             |
    |      Block       |     |Village.                    |    6.8.2001     |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 82 |    Mawsynram     |1999-| 2. Construction of         | Rs.   30,000 /- | Rs.   30,000 /- |   -do-        |             |
    |   Development    |2000 | Footbridge at Kharbri      |                 |                 |               |             |
    |      Block       |     |Village, Bhowal Syiemship.  |    6.8.2001     |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 83 |    Mawsynram     |1999-| 3. Construction of Footpath| Rs.   20,000 /- | Rs.   20,000 /- |   -do-        |             |
    |   Development    |2000 |at Mawkaphan Village.       |    6.8.2001     |                 |               |             |
    |      Block       |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 84 |    Mawsynram     |1999-| 4. Construction of         | Rs.   30,000 /- | Rs.   30,250 /- |   -do-        |             |
    |   Development    |2000 |Community Hall at Dewsawlia |     6.8.2001    |                 |               |             |
    |      Block       |     |Village.                    |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 85 |    Mawsynram     |1999-| 5. Construction of         | Rs.   80,000 /- | Rs.   80,000 /- |   -do-        |             |
    |   Development    |2000 |Cultural Playground at      |                 |                 |               |             |
    |      Block       |     |Lawbah.                     |  27-11-2001     |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 86 |    Mawsynram     |1999-| 6. Construction of         | Rs.   20,000 /- | Rs.   20,000 /- |   -do-        |             |
    |   Development    |2000 |Community Hall at Umniang   |  21-12-2001     |                 |               |             |
    |      Block       |     |Village, Mawdon Syiemship.  |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 87 |    Mawsynram     |1999-| 7. Construction of         | Rs.   30,000 /- | Rs.   30,500 /- |   -do-        |             |
    |   Development    |2000 |Community Hall at Kmawan,   |  13.06.2002     |                 |               |             |
    |      Block       |     |Ponkung.                    |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 88 |    Mawsynram     |1999-| 8. Construction of footpath| Rs.   20,000 /- |                 |               |             | Not sanction pending
    |   Development    |2000 |from Umtynriew to Nongkriah |                 |                 |               |             | submission of plan and
    |      Block       |     |Village.                    |                 |                 |               |             | estimate, execution
    |                  |     |                            |                 |                 |               |             | of agreement.
-----------------------------------------------------------------------------------------------------------------------------------------------------
 89 |    Mawsynram     |1999-| 9. Extension of School     | Rs. 1,00,000 /- | Rs. 1,00,000 /- |  Completed    |             |
    |   Development    |2000 |building of Mawsynram       |     13-3-2002   |                 |               |             |
    |      Block       |     |Higher Secondary School     |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
 90 |    Mawsynram     |1999-|10. Construction of         | Rs.   30,000 /- | Rs.   30,000 /- |   In Progress |             |
    |   Development    |2000 |Playground at Nonglait.     |     13-6-2002   |                 |               |             |
    |      Block       |     |                            |                 |                 |               |             |
    |                  |     |                            |                 |                 |               |             |
-----------------------------------------------------------------------------------------------------------------------------------------------------
         Grand Total   |               90 Nos              Rs. 1,41,43,234/-|                 |
-----------------------------------------------------------------------------------------------------------------------------------------------------