STATEMENT SHOWING PROGRESS OF WORKS/SCHEMES UNDER M.P. LOCAL AREA DEVELOPMENT SCHEME
FOR THE YEAR 2002-2003
------------------------------------------------------------------------------------------------------------------------------------------------------
Name of the M.P SHRI R. KHARSHIING
------------------------------------------------------------------------------------------------------------------------------------------------------
Name of the Block|Year | Name of the Schemes |Amount Approved | Amount Utilised |Status/ |Date/Expected |Reasons for delay
| | |by MP sanctioned | As on 31.10.2007 |Position |Date of Comple|in completion
| | | with Date | |of the |tion |
| | | | |Scheme | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF CLASS ROOM ON THIRD | Rs. 1,00,000.00 | Rs. 1,00,000.00 |COMPLETED|
| |FLOOR OF SYNOD COLLEGE AT | 07/04/2003 | | |
| |JAIAW SHILLONG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF MAWPAT PLAYGROUND | Rs. 2,00,000.00 | Rs. 2,00,000.00 |COMPLETED| |
| | | 30/06/2002 | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF MOTORABLE ROAD AT | Rs. 75,000.00 | Rs. 75,000.00 |COMPLETED|
| |DONG MARBOH (NONGRAH) | 17/12/2002 | | | |
| | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF FOOTPATH AT DONG | Rs. 30,000.00 | Rs. 30,000.00 |COMPLETED| |
| |NONGLUM NONGRAH VILLAGE | 30/06/2003 | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF BORE WELL IN | Rs. 50,000.00 | Rs. 50,000.00 |COMPLETED| |
| |AUXILIUM SCHOOL | 30/06/2003 | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF PUBLIC FOOTPATH | Rs. 1,78,000.00 | Rs. 1,78,000.00 |COMPLETED| |
| |ADJACENT TO ART CULTURE | | | |
| |PRESBYTERIAN | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF LANE AT RILBONG | Rs. 22,000.00 | Rs. 22,000.00 |COMPLETED|
| |STARTING FROM MR. A HAQUE | | | |
| |HOUSE TO MR. M. AHMED | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|PURCHASE INSTALLATION OF 5 | Rs. 4,40,000.00 |Rs. 3,36,150.00 COMPLETED| |
| |COMPUTER,HARDWARE SOFTWARE | | | |
| |SYSTEM, FURNITURE AND TRAINING | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|PURCHASE INSTALLATION OF 5 | Rs. 4,40,000.00 | 3,36,150.00 |COMPLETED |
| |COMPUTERS,HARDWARE SOFTWARE | | | | |
| |SYSTEM,FURNITURE, 2 YEARS | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF SLAB-DRAIN-CUM FOOT- | Rs. 1,50,000.00 | Rs. 1,50,000.00 |Completed|
| |PATH AT MAWLAI NONGPDENG,
| |SHILLONG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF RETAINING WALL FOR | Rs. 50,000.00 | Rs. 50,000.00 |Completed|
| |SACRED HEART BOY'S HIGHER | | | |
| |SECONDARY SCHOOL CAMPUS MAWLAI | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|IMPROVEMENT OF WATER SUPPLY | Rs. 50,000.00 | Rs. 50,000.00 |Completed|
| |AT LAWSOHTUN | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF FOOTPATH AT | Rs. 25,000.00 | Rs. 25,000.00 |Completed| |
| |LAWSOHTUN | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF STAFF QUARTER FOR | Rs. 2,00,000.00 | Rs. 2,00,000.00 Completed |
| |RILBONG L.P SCHOOL, SHILLONG | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|EXPANSION/CONST. OF SMALL | Rs. 60,000.00 | Rs. 60,000.00 |Completed|
| |SCALE INDUSTRY CENTRE AT | | | |
| |UPPER MALKI, SHILLONG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. OF SCHOOL AUDITORIUM IN | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed|
| |GORKHA PATHSHALA HIGHER | | | | |
| |SECONDARY SCHOOL, MAWPREM | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mylliem Block |02-03|CONST. INCLUDING METALLING-CUM | Rs. 2,00,000.00 | Rs. 2,00,000.00 | |
| |BLACK TOPPING OF ROAD AT RIAT- | | |Completed|
| |SOHKHLUR 3rd MILE NONGKSEH | | | |
| |UPPER SHILLONG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Shella Block |02-03|CONST. OF FOOTPATH FROM KATO | Rs. 50,000.00 | Rs. 50,000.00 | |
| |LBA SHELLA | 30/06/2003 | |completed| |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Shella Block |02-03|CONST. OF PLAYGROUND AT | Rs. 1,00,000.00 | Rs. 1,00,000.00 | | |
| |WAHKALIAR VILLAGE | | |Completed| |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Shella Block |02-03|CONST. OF NEW BUILDING WAHADA- | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed|
| |DAR ROBISON SYNGWAN MEMORIAL | | | |
| |HIGH SCHOOL SOHLAP | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Shella Block |02-03|CONST. OF HOSTEL FOR CHRISTIAN | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed |
| |CHILDREN HOME(ORPHANAGE) AT | | | |
| |POMSOHMEN | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Shella Block |02-03|CONST. OF OFFICE BUILDING-CUM- | Rs. 50,000.00 | Rs. 50,000.00 |Completed|
| |I.B AT BHOLAGANJ, SOHRA | | | | |
| |SYIEMSHIP | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Shella Block |02-03|CONST. OF DORBAR HALL IN | Rs. 2,00,000.00 | Rs. 2,00,000.00 |Completed|
| |HIMA SOHRA | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Pynursla Block |02-03|IMPROVEMENT OF FOOTBALL FIELD | Rs. 30,000.00 | Rs. 30,000.00 |Completed| |
| |AT PDENGSHNONG WAHSKONG | | | |
| |NONGJRI | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 90,000.00 | Rs. 90,000.00 |Completed| |
| |MAWKAPHAN VILLAGE | 25/03/2003 | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF CEMENTED FOOTPATH | Rs. 50,000.00 | Rs. 50,000.00 |Completed| |
| |FROM PWD ROAD TO PDENGSHNONG | 25/03/2003 | | | |
| |MAWRAPAD VILLAGE | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF PUCCA CEMENTED FOOT- | Rs. 60,000.00 | Rs. 60,000.00 |Completed| |
| |PATH CUM-CONST. OF DRAIN BY | | | |
| |THE SIDE OF FOOTBALL PLAY | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF PLAYGROUND AT | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed | |
| |MAWSYNRAM BORDER AREA COLLEGE | | | |
| |CAMPUS | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|PURCHASE INSTALLATION OF 5 | Rs. 4,40,000.00 | Rs.3,36,000/- | | |
| |COMPUTERS HARDWARE SOFTWARE | | |completed|
| |SYSTEM, FURNITURE&TRAINING | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 2,00,000.00 | Rs. 2,00,000.00 |Completed |
| |HAT MAWDON | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF COMMUNITY HALL-CUM- | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed| |
| |COURT ROOM AT MAWSYNRAM | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed| |
| |DANGAR DOMBAH | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawsynram Block |02-03|CONST. OF DORBAR HALL AT | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed| |
| |THYLLAW | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF VILLAGE DURBAR HALL | Rs. 50,000.00 | Rs. 50,000.00 |Completed| |
| |AT LUMSOHRIEW MAWKALUM VILLAGE | 07/04/2003 | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF SCHOOL BUILDING AT | Rs. 2,00,000.00 | Rs. 2,00,000.00 |Completed| |
| |MAWPHLANG PROCEEDING SECONDARY
| |SCHOOL | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|PURCHASE INSTALLATION OF 5 | Rs. 4,40,000.00 Rs.3,36,000/- |Completed| |
| |COMPUTERS HARDWARE SOFTWARE | | |
| |SYSTEM, FURNITURE AND TRAINING |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF COMMUNITY HALL CUM- | Rs. 2,00,000.00 | Rs. 2,00,000.00 |Completed| |
| |INDOOR SPORT HALL AT LUMSOH-
| |KHLUR NONGBAH, SOHIONG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF TRAINING CENTRE AT | Rs. 1,00,000.00 | Rs. 1,00,000.00 Completed| |
| |MAWPHLANG | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 1,50,000.00 | Rs. 1,50,000.00 Completed| |
| |MARBISU | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 1,50,000.00 | Rs. 1,50,000.00 Completed| |
| |MAWPHLANG | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF CEMENT PLATFORM TO | Rs. 20,000.00 | Rs. 20,000.00 |Completed | |
| |SEAT DRUMMER AND FLUTIST | | | |
| |LAITMAWSHING | | | | |
--------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 1,50,000.00 | Rs. 1,50,000.00 Completed| |
| |MARBISU | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF COMMUNITY HALL AT | Rs. 1,50,000.00 | Rs. 1,50,000.00 |Completed| |
| |MAWPHLANG | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF TRAINING CENTRE AT | Rs. 1,00,000.00 | Rs. 1,00,000.00 Completed| |
| |MAWPHLANG | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF COMMUNITY-CUM-INDOOR | Rs. 2,00,000.00 | Rs. 2,00,000.00 |Completed| |
| |SPORT HALL AT LUMSOHKHLUR | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|PURCHASE & INSTALLATION 5 | Rs. 4,40,000.00 | Rs.3,36,000/- Completed |
| |CUMPUTERS HARDWARE ETC KYIEM | | | |
| |PROCEEDING HIGH SCHOOL | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF SCHOOL BUILDING AT | Rs. 2,00,000.00 | Rs. 2,00,000.00 | | |
| |MAWPHLANG PROCEEDING SECONDARY | | Completed| |
| |SCHOOL | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawphlang Block |02-03|CONST. OF VILLAGE DURBAR HALL | Rs. 50,000.00 | Rs. 50,000.00 |Completed| |
| |AT LUMSOHRIEW MAWKALUM | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|IMPROVEMENT OF FOOTBALL GROUND | Rs. 25,000.00 | Rs. 25,000.00 |COMPLETED| |
| |AT KUT VILLAGE(DONG RNGI)
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|CONST. OF COMMUNITY HALL AT | Rs. 75,000.00 | Rs. 75,000.00 |COMPLETED| |
| |DONG IEWRIM PURIANG | 30/06/2003 | | | |
| | | | | | |
-----------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|CONST. OF BUS SHED STOP FOR | Rs. 25,000.00 | Rs. 25,000.00 |Completed| |
| |PUBLIC TRANSPORT PASSENGER AT | | | |
| |KUT WAHIINGKIENG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|CONST. OF BUS SHED STOP FOR | Rs. 25,000.00 | Rs. 25,000.00 Completed| |
| |PUBLIC TRANSPORT PASSENGERS
| |AT PURIANG MAWKAJUT | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|CONST. OF BASKET BALL | Rs. 50,000.00 | Rs. 50,000.00 |Completed| |
| |PLAYGROUND COURT AT RISING SUN | | | |
| |SCHOOL, MAWRYNGKNENG | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|IMPROVEMENT OF PLAYGROUND AT | Rs. 25,000.00 | Rs. 25,000.00 |COMPLETED| |
| |DONG JONGKHLA (KUT VILLAGE)
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|CONST. OF DAM AT MAWPYRSHONG | Rs. 50,000.00 | Rs. 50,000.00 |Completed| |
| |VILLAGE | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawryngkneng Block|02-03|CONST. OF SCHOOL BUILDING OF | Rs. 30,000.00 | Rs. 30,000.00 |Completed| |
| |RCLP SCHOOL THADAN | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawkynrew Block |02-03|CONST. OF LYNSHING PLAYGROUND | Rs. 1,00,000.00 | Rs. 1,00,000.00 | | |
| | | 30/06/2003 | |completed| |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawkynrew Block |02-03|CONST. OF SYNTUNG PLAYGROUND | Rs. 1,00,000.00 | Rs. 1,00,000.00 | | |
| | | 30/06/2003 | |completed| |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawkynrew Block |02-03|CONST. OF MADAN THANGSNING | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed | |
| |L.P SCHOOL AT MADAN THANGSNING | | | |
| |(KHYRIM SYIEMSHIP) | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawkynrew Block |02-03|CONST.OF APROACH RD FROM SMIT | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed| |
| |MAWLAT ROAD TO JOHN'S HERBAL | | | | |
| |NURSING CARE AT THANGSNING | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Mawkynrew Block |02-03|IMPROVEMENT OF FOOTBALL FIELD | Rs. 20,000.00 | Rs. 20,000.00 | | |
| |AT RANGPHLANG | | |completed| |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Laitkroh Block |02-03|COMPLETION OF VOCATIONAL | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed| |
| |TRAINING SCHOOL AT LAITLYNGKOT | | | | |
| |UNDER LYNGKYRDEM DEVELOPMENT | | | | |
| |ASSOCIATION | | | | |
| | | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Laitkroh Block |02-03|PURCHASE INSTALLATION OF 5 | Rs. 4,40,000.00 | Rs.3,36,000/- |Completed |
| |COMPUTERS HARDWARE SOFTWARE | | | |
| |SYSTEM, FURNITURE & TRAININ | | | |
| |OF 2 TEACHERS AT LAITLYNGKOT | | | |
| |SECONDARY SCHOOL, LAITLYNGKOT | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Laitkroh Block |02-03|CONST. OF VOCATIONAL TRAINING | Rs. 1,00,000.00 | Rs. 1,00,000.00 |Completed |
| |SCHOOL AT LAITLYNGKOT | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------
Laitkroh Block |02-03|PURCHASE OF EQUIPMENTS AND | Rs. 50,000.00 | Rs.50,000/- Completed |
| |ACCESSORIES FOR MULTIPURPOSE | | | |
| | SOCIAL WELFARE ORGANISATION, | | | |
| |MAWJRONG | | | | |
| | | | | | |
| | | | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------