PROGRESS REPORT ON IMPLEMENTATION OF CRRP SCHEMES
FOR THE YEAR 2002-2003
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
| Name of Block | Name of Hon'ble|Year | No. of | Name of Project | Amount | Amount | Letter No. | Amount |Status |Balance |Reason |Remarks
| | MLA | |Projects| | |sanc- | & date of |utilised |of work|amount if |for delay |
| | |recom- | | |tioned |sanctioned |upto |in % |any at |/incom- |
| | |mended | | |to DRDA |to DRDA |30.04.06 | |the Block |pletion |
| | | | | |/Block |/Block |at Block | | | |
------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
| MYLLIEM | R.A LYNGDOH-MLA|02-03| 1 | 1) IMPROVEMENT OF FOOTPATH | 14,000| 14,000|MEMO NO.DEV.35(VII)2/2002/35-A| 7,000 | | 7,000 | |
| DEV. BLOCK | | | | LEADING TO PUNG TONGUM UMKOI | | |DT. 18-11-2002 | | | | |
| | | | | LAWMEI | | | | | | | |
| MYLLIEM | P.M SYIEM-MLA |02-03| 4 | CONST. OF C.D FOOTPATH AT :- | | | | | | | |
| DEV. BLOCK | 15-MYLLIEM | | | 1) UPPER MYLLIEM | 1,00,000| 4,28,571|- DO - | 1,00,000|100 % |NIL |COMPLETED |
| | | | | 2) LOWER MYLLIEM | 1,00,000| |- DO - | 1,00,000|100 % |NIL |COMPLETED |
| | | | | 3) UPPER SHILLONG | 1,00,000| |- DO - | 1,00,000|100 % |NIL |COMPLETED |
| | | | | 4) LOWER UPPER SHILLONG | 1,28,571| |- DO - | 1,28,571|100 % |NIL |COMPLETED |
| MYLLIEM | T.C LYNGDOH-MLA|02-03| 15 | 1) CONST. OF FOOTPATH (1.0m) | 11,000| 4,28,571|- DO - | 5,000| 50 % | 6,000 |IN PROGRESS
| | | | | WIDE FROM THE RESIDENCE OF | | | | | | | |
| | | | | SMT. GRACY KHARKONGOR UPTO AN | | | | | | | |
| | | | | ELECTRIC POLE NEAR THE RESI- | | | | | | | |
| | | | | DENCE OF KONG SI MARWEIN AT | | | | | | | |
| | | | | LUMDEMTHRING SHILLONG | | | | | | | |
| | | | | 2) CONST. OF FOOTPATH FROM THE| 39,700| | | 39,700|100 % |NIL |COMPLETED |
| | | | | RESIDENCE OF Mrs.R.SYIEMIONG | | | | | | | |
| | | | | TO Mrs.M.LALOO AT LAWJYNRIEW | | | | | | | |
| | | | | NONGTHYMMAI SHILLONG | | | | | | | |
| | | | | 3) CONST.OF FOOTPATH FROM THE | 37,000| |- DO - | 37,000|100 % |NIL |COMPLETED |
| | | | | RESIDENCE OF Mr S.PHAI TO Mr. | | | | | | | |
| | | | | T. NONGSIEJ AT LAWJYNRIEW | | | | | | | |
| | | | | NONGTHYMMAI SHILLONG | | | | | | | |
| | | | | 4) CONST.OF FOOTPATH FROM THE | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | PWD ROAD TO THE RESIDENCE OF | | | | | | | |
| | | | | Mr R. SHONGWAN AT LAWJYNRIEW | | | | | | | |
| | | | | NONGTHYMMAI, SHILLONG | | | | | | | |
| | | | | 5) CONST.OF FOOTPATH CUM-DRAIN| 26,000| |- DO - | 26,000|100 % |NIL |COMPLETED |
| | | | | NAR MADAN HINDI PATSALA SCHOOL| | | | | | | |
| | | | | MADANRTING, SHILLONG | | | | | | | |
| | | | | 6) CONST. OF FOOTPATH AT THEM | 9,000| |- DO - | 9,000|100 % |NIL |COMPLETED |
| | | | | BASUK NEAR THE HOUSE OF KONG | | | | | | | |
| | | | | IBON NONGDHAR MADANRTING, SHG.| | | | | | | |
| | | | | 7) CONST. OF FOOTPATH& U-SHAPE| 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | DRAIN OPPOSITE THE HOUSE OF | | | | | | | |
| | | | | HOLAS KHARKONGOR AT MADANRTING| | | | | | | |
| | | | | SHILLONG | | | | | | | |
| | | | | 8) CONST. OF FOOTPATH& V-SHAPE| 15,300| |- DO - | 15,300|100 % |NIL |COMPLETED |
| | | | | DRAIN NEAR THE HOUSE OF BIDI | | | | | | | |
| | | | | KHARKONGOR UPTO THE CATHOLIC | | | | | | | |
| | | | | CHURCH MADANRTING, SHILLONG | | | | | | | |
| | | | | 9) CONST. OF FOOTPATH & DRAIN | 58,000| |- DO - | 58,000|100 % |NIL |COMPLETED |
| | | | | NEAR THE HOUSE OF TROS MAI | | | | | | | |
| | | | | KHARKRANG TO MIDDLE KHARKONGOR| | | | | | | |
| | | | | AT MADANRTING SHILLONG | | | | | | | |
| | | | | 10) EXTENSION OF AN EXISTING | 24,000| |- DO - | 24,000|100 % |NIL |COMPLETED |
| | | | | FOOTPATH FROM Mrs L.W SYIEM- | | | | | | | |
| | | | | LIEH RESIDENT UPTO THE | | | | | | | |
| | | | | PROPOSED PWD ROAD AT | | | | | | | |
| | | | | MADANRTING BLOCK F | | | | | | | |
| | | | | 11) CONST. OF FOOTPATH-CUM- | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | MOTORABLE ROAD FROM THE RESI- | | | | | | | |
| | | | | DENCE OF SMT.V.KHYRIEM UPTO | | | | | | | |
| | | | | THE RESIDENCE OF SMT. SIL | | | | | | | |
| | | | | KHYRIEM AT LUMDEMTHRING SHG. | | | | | | | |
| | | | | 12) CONST. OF FOOTPATH AT | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | SHYNGIAR DONG PATA MADANRTING | | | | | | | |
| | | | | 13) CONST. OF FOOTPATH-CUM- | 4,000| |- DO - | 4,000|100 % |NIL |COMPLETED |
| | | | | MOTORABLE ROAD NEAR THE HOUSE | | | | | | | |
| | | | | OF SHRI BUAM SHULLAI, PATA, | | | | | | | |
| | | | | MADANRTING SHILLONG | | | | | | | |
| | | | | 14) CONST. OF FOOTSTEPS AND | 24,000| |- DO - | 24,000|100 % |NIL |COMPLETED |
| | | | | FOOTPATH AT PYNTHOR, PATA, | | | | | | | |
| | | | | MADANRTING, SHILLONG | | | | | | | |
| | | | | 15) CONST. OF FOOTPATH CUM- | 60,571| |- DO - | 60,571|100 % |NIL |COMPLETED |
| | | | | MOTORABLE ROAD NEAR THE | | | | | | | |
| | | | | RESIDENCE OF SMT. GRACY KHAR- | | | | | | | |
| | | | | KONGOR UPTO THE PUBLIC TAP AT | | | | | | | |
| | | | | LUMDEMTHRING, SHILLONG | | | | | | | |
| BDO MYLLIEM | R.G LYNGDOH-MLA|02-03| 7 | 1) CONST. OF MOTORABLE ROAD | 90,000| 4,28,571|NO.DEV.35(VII)2/2002/36 | 90,000|100 % |NIL |COMPLETED |
| DEV. BLOCK | | | | INCLUDING SLAB DRAIN FROM NEAR| | |DT. 18-11-02 | | | | |
| | | | | THE RESIDENCE OF Mr BUCKLAN | | | | | | | |
| | | | | KHONGWIR UPTO NEAR THE | | | | | | | |
| | | | | RESIDENCE OF Mr. C.H DIENGDOH | | | | | | | |
| | | | | 2) CONST. OF C.C FOOTPATH BY | 1,53,371| |- DO - | 1,53,371|100 % |NIL |COMPLETED |
| | | | | THE RESIDENCE OF SHRI G.MAWRIE| | | | | | | |
| | | | | UPTO POHKTIEH MAIN ROAD | | | | | | | |
| | | | | 3) DRAIN FROM NEAR THE | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | RESIDENCE OF BAILIN KHARKONGOR| | | | | | | |
| | | | | UPTO THE RESIDENCE OF H.O | | | | | | | |
| | | | | KHARKONGOR | | | | | | | |
| | | | | 4) DRAIN CONNECTING RESIDENCE | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | OF SERIA MARWEIN AND BAH BOK | | | | | | | |
| | | | | KHARKONGOR KONG EBEL RNGI KSEH| | | | | | | |
| | | | | 5) DRAIN CONNECTING RESIDENCE | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | OF KONG KSHIR,KONG KHARSYNTIEW| | | | | | | |
| | | | | PRESBYTERIAN CHURCH AND OTHERS| | | | | | | |
| | | | | 6) REPAIR OF FOOTPATH AT DUM | 41,000| |- DO - | 41,000|100 % |NIL |COMPLETED |
| | | | | DUM TOWARDS THE RESIDENCE OF | | | | | | | |
| | | | | D. NONGRUM | | | | | | | |
| | | | | 7) CONST. OF FOOTPATH FROM PWD| 24,200| |- DO - | 24,200|100 % |NIL |COMPLETED |
| | | | | ROAD UPTO THE RESIDENCE OF | | | | | | | |
| | | | | SMT. BROSI W. SYNREM | | | | | | | |
| BDO MYLLIEM | A.L HEK-MLA |02-03| 6 | 1) CONST. OF A RETAINING WALL | 2,00,000| 4,28,571|MEMO NO.DEV.35(VII)2/2002/35-A| 2,00,000|100 % |NIL |COMPLETED |
| | | | | AND DRAINAGE SYSTEM OF GOLF | | |DT. 18-11-02 | | | | |
| | | | | LINK PDENGSHNONG | | | | | | | |
| | | | | 2) CONST. OF FOOTPATH AT | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | LUMSHIAP | | | | | | | |
| | | | | 3) CONST. OF DRAIN & FOOTPATH | 50,000| | | 50,000|100 % |NIL |COMPLETED |
| | | | | AT LAWMALI | | | | | | | |
| | | | | 4) CONST. OF A RETAINING WALL | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | AND CULVERT AT PYNTHORBAH | | | | | | | |
| | | | | 5) CONST. OF FOOTBRIDGE AND | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | FOOTPATH AT NONGMENSONG | | | | | | | |
| | | | | 6) CONST. OF FOOTPATH AT | 28,571| |- DO - | 28,571|100 % |NIL |COMPLETED |
| | | | | FOREST COLONY | | | | | | | |
| BDO MYLLIEM | P.T SAWKMIE-MLA|02-03| 24 | 1) IMPROVEMENT OF FOOTPATH AT | 20,000| 4,28,571|MEMO NO.DEV.35(VII)2/2002/35-A| 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI UMTHLONG | | | | | | | |
| | | | | 2) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI NONGKWAR | | | | | | | |
| | | | | 3) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI IEWRYNGHEP | | | | | | | |
| | | | | 4) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI NONGLUM | | | | | | | |
| | | | | 5) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI NONGPDENG | | | | | | | |
| | | | | 6) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI PHUDMAWRI | | | | | | | |
| | | | | 7) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI DATBAKI | | | | | | | |
| | | | | 8) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI MAWROH | | | | | | | |
| | | | | 9) IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI KYNTON MASSAR | | | | | | | |
| | | | | 10) IMPROVEMENT OF FOOTPATH AT| 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI SYLLAIKARIAH | | | | | | | |
| | | | | 11) IMPROVEMENT OF FOOTPATH AT| 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI MOTSYIAR | | | | | | | |
| | | | | 12)IMPROVEMENT OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI UMJAIUR | | | | | | | |
| | | | | 13) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI MAWTAWAR | | | | | | | |
| | | | | 14) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | MAWLAI UMSHING MAWKYNROH | | | | | | | |
| | | | | 15) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | LUM MAWSING | | | | | | | |
| | | | | 16) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | UMSAW MAWJYNRONG | | | | | | | |
| | | | | 17) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | NONGKOHLEW | | | | | | | |
| | | | | 18) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | MAWSIATKHNAM | | | | | | | |
| | | | | 19) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | UMRYNJAH | | | | | | | |
| | | | | 20) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | UMPHREW | | | | | | | |
| | | | | 21) IMPROVEMENT OF FOOTPATH AT| 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | MADAN MAWKHAR | | | | | | | |
| | | | | 22) IMPROVEMENT OF FOOTPATH AT| 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWIONG UMJAPUNG | | | | | | | |
| | | | | 23) IMPROVEMENT OF FOOTPATH AT| 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWIONG RIM | | | | | | | |
| | | | | 24) IMPROVEMENT OF FOOTPATH AT| 13,571| |- DO - | 13,571|100 % |NIL |COMPLETED |
| | | | | MAWLAI CHRISTIAN SCHOOL | | | | | | | |
| | S.S LYNGDOH-MLA|02-03| 2 | 1) CONST. OF MOTORABLE ROAD | 1,50,000| 2,00,000|MEMO NO.DEV.35(VII)2/2002/35 | 1,50,000|100 % |NIL |COMPLETED |
| | | | | FROM DONG UMBAH JUNCTION TO | | |DT. 18-11-02 | | | | |
| | | | | DONGSHANENG UMPLING | | | | | | | |
| | | | | 2) CONST. OF FOOTPATH AT | 50,000| |- D0 - | 50,000|100 % |NIL |COMPLETED |
| | | | | MAWPAT | | | | | | | |
| | E.R KHARKONGOR |02-03| 8 | 1) CONST. OF FOOTPATH AT | 25,000| 1,95,000|MEMO NO.DEV.35(VII)2/2002/35 | 25,000|100 % |NIL |COMPLETED |
| | | | | KHARPOR LAITKOR NONGDANENG | | | | | | | |
| | | | | 2) CONST. OF FOOTPATH AT | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | LAITKOR, LAITKOR LUMHEH | | | | | | | |
| | | | | 3) CONST. OF FOOTPATHA AT RNGI| 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | SHILLONG, POMLAKRAI | | | | | | | |
| | | | | 4) CONST. OF FOOTBRIDGE AT | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | RNGI SHILLONG, POMLAKRAI | | | | | | | |
| | | | | 5) CONST. OF FOOTPATH AT | 25,000| |- DO - | 11,500| 30 % |13,500 |IN |
| | | | | LIEWLONG POMLAKRAI | | | | | | |PROGRESS |
| | | | | 6) CONST. OF FOOTPATH AT | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | LAWSOHTUN | | | | | | | |
| | | | | 7) CONST. OF MOTORABLE ROAD AT| 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | PDENGSHNONG MAWPYNTHIH | | | | | | | |
| | | | | 8) CONST. OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWPYNTHIH | | | | | | | |
| BDO MAWPHLANG | J.A LYNGDOH-MLA|02-03| 20 | 1) CONST. OF FOOTPATH TOWARDS | 15,000| 3,83,571|MEMO NO.DEV.35(VII)2/2002/36-A| 15,000|100 % |NIL |COMPLETED |
| | | | | BALANG JISU KRIST MADAN BITAW | | |DT. 18-11-02 | | | | |
| | | | | 2) CONST. OF FOOTPATH TOWARDS | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | BALANG U BLEI, MADAN BITAW | | | | | | | |
| | | | | 3) CONST. OF FOOTPATH TOWARDS | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | BALANG JINGIASYLLOK MADAN | | | | | | | |
| | | | | BITAW | | | | | | | |
| | | | | 4) CONST. OF FOOTPATH TOWARDS | 15,000| | | 7,500| 70 % | 7,500 | |U.C TO BE RECEIVED
| | | | | LAIT RYNGWAI | | | | | | | |
| | | | | 5) CONST. OF SLAP DRAIN CUM | 25,000| | | 25,000|100 % |NIL |COMPLETED |
| | | | | FOOTPATH FROM PWD ROAD TO THE | | | | | | | |
| | | | | RESIDENCE OF Mr BASON MAWLONG | | | | | | | |
| | | | | 6) CONST. OF FOOTPATH AT WAH | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | LYNGKIEN | | | | | | | |
| | | | | 7) CONST. OF FOOTPATH AT | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | SARONG VILLAGE | | | | | | | |
| | | | | 8) CONST. OF FOOTPATH FROM PWD| 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | ROAD TO GRAVE YARD MAWSER | | | | | | | |
| | | | | (NONGLWAI) | | | | | | | |
| | | | | 9) CONST. OF FOOTPATH AT THAIN| 20,000| | | 20,000|100 % |NIL |COMPLETED |
| | | | | THYNROH | | | | | | | |
| | | | | 10) CONST. OF FOOTPATH AT | 25,000| | | 25,000|100 % |NIL |COMPLETED |
| | | | | SNAIBAI MAWMOHWAR | | | | | | | |
| | | | | 11) IMPROVEMENT OF MOTORABLE | 25,000| | | 25,000|100 % |NIL |COMPLETED |
| | | | | ROAD AT LYNGDOH PHANBLANG | | | | | | | |
| | | | | 12) CONST. OF FOOTPATH AT | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | LAWKHLA LAITDIKER | | | | | | | |
| | | | | 13) CONST. OF FOOTPATH AT | 33,571| | | 33,571|100 % |NIL |COMPLETED |
| | | | | LYNGKIEN TANGREW | | | | | | | |
| | | | | 14) IMPROVEMENT OF MOTORABLE | 20,000| | | 20,000|100 % |NIL |COMPLETED |
| | | | | ROAD AT KNER LYNGDOH LYNGKHOI | | | | | | | |
| | | | | WORK TO BE DONE BY SHRI S. | | | | | | | |
| | | | | LYNGDOH | | | | | | | |
| | | | | 15) CONST. OF FOOTPATH AT | 20,000| | | 20,000|100 % |NIL |COMPLETED |
| | | | | WEIPYLLUN ADVENTIST SCHOOL | | | | | | | |
| | | | | 16) CONST. OF FOOTPATH FROM | 20,000| | | 20,000|100 % |NIL |COMPLETD |
| | | | | MAWKNENG PLAYGROUND TO LUMKSEH| | | | | | | |
| | | | | 17) CONST. OF FOOTBRIDGE AT | 25,000| | | 25,000|100 % |NIL |COMPLETED |
| | | | | STEW NONGLWAI WORK TO BE DONE | | | | | | | |
| | | | | BY SHRI B. JYRWA, HEADMAN | | | | | | | |
| | | | | 18) CONST. OF FOOTPATH AT | 20,000| | | 20,000|100 % |NIL |COMPLETED |
| | | | | DEWSAW | | | | | | | |
| | | | | 19) CONST. OF FOOTPATH AT | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | MAWMYRSIANG | | | | | | | |
| | | | | 20) CONST. OF FOOTPATH AT | 15,000| | | 15,000|100 % |NIL |COMPLETED |
| | | | | RINEM MAWKROH NONGSPUNG | | | | | | | |
| | R.A LYNGDOH-MLA|02-03| 8 | 1) CONST. OF FOOTPATH FROM PWD| 14,000| 1,14,571|MEMO DEV.35(VII)2/2002/36-A, | 14,000|100 % |NIL |COMPLETED |
| | | | | ROAD TO CHURCH OF GOD SCHOOL | | |DT. 18-11-02 | | | | |
| | | | | TIEHBAH | | | | | | | |
| | | | | 2) CONST. OF FOOTPATH LEADING | 13,000| |- DO - | 13,000|100 % |NIL |COMPLETED |
| | | | | TO ROMAN CATHOLIC CHURCH | | | | | | | |
| | | | | NONGKSEH VILLAGE(LAITNONGKSEH)| | | | | | | |
| | | | | 3) CONST. OF FOOTPATH AT DOM | 14,000| |- DO - | 14,000|100 % |NIL |COMPLETED |
| | | | | MAWKSIAR, LEN MAWTAP-SOHIONG | | | | | | | |
| | | | | (WORKS TO BE IMPLEMENTED BY | | | | | | | |
| | | | | SHRI BALOM MAWLONG) | | | | | | | |
| | | | | 4) IMPROVEMENT OF ROAD FROM | 20,000| |- DO - | 20,000|100 & |NIL |COMPLETED |
| | | | | DOMSHOIN TO UMSOHIONG VILLAGE | | | | | | | |
| | | | | 5) IMPROVEMENT OF ROAD LEADING| 14,000| |- DO - | 14,000|100 % |NIL |COMPLETED |
| | | | | TO THE SOURCES OF WATER AT | | | | | | | |
| | | | | NONGING | | | | | | | |
| | | | | 6) CONST. OF FOOTPATH AT | 14,571| |- DO - | 14,571|100 % |NIL |COMPLETED |
| | | | | MAWMAIANG LEADING TO CATHOLIC | | | | | | | |
| | | | | CHURCH | | | | | | | |
| | | | | 7) CONST. OF FOOTPATH LEADING | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | TO PUNG TONGUM AT MADAN KOR | | | | | | | |
| | | | | 8) IMPROVEMENT OF FOOTPATH AT | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | NONGBAH SOHIONG | | | | | | | |
| BDO MAWKYNREW | M.N MUKHIM-MLA |02-03| 7 | 1) PIDC UMTONG FOR IMPROVEMENT| 70,000| 3,08,571|MEMO NO.DEV.35(VII)2/2002/37-A| 70,000|100 % |NIL |COMPLETED |
| | | | | I/C M&B OF MAWLALI VILLAGE | | |DT. 18-11-02 | | | | |
| | | | | ROAD (PHASI-II) | | | | | | | |
| | | | | 2)PIDC UMTONG FOR IMPROVEMENT | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | OF ROAD FROM PWD ROAD TO | | | | | | | |
| | | | | LAITMAWPHAN, THYNROIT | | | | | | | |
| | | | | 3) CONST. OF APPROACH ROAD TO | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | PDENGSHNONG MAWJATAP | | | | | | | |
| | | | | 4) IMPROVEMENT OF ROAD FROM | 30,000| | | 80,000|100 % |NIL |COMPLETED |
| | | | | LUMEITKUI TO SYLLAI U SON | | | | | | | |
| | | | | NIANGWAIN , THYNROIT | | | | | | | |
| | | | | 5) IMPROVEMENT OF NONGSPUNG | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | LANGSAH ROAD, THYNROIT | | | | | | | |
| | | | | 6) IMPROVEMENT OF ROAD NEAR | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | THE COMPOUND OF BAH GALAND | | | | | | | |
| | | | | KHARMUDAI, KHARANG | | | | | | | |
| | | | | 7) IMPROVEMENT OF ROAD FROM | 48,571| |- DO - | 48,571|100 % |NIL |COMPLETED |
| | | | | PWD TO MAWSYNJRI | | | | | | | |
| | E.R KHARKONGOR |02-03| 1 | 1) CONST. OF FOOTBRIDGE AT | 33,571| 33,571|MEMO NO/DEV.35(VII)2/2002/37-A| 33,571|100 % |NIL |COMPLETED |
| | MLA | | | UMKYNRUH, LAITLUM | | |DT. 8-11-02 | | | | |
| | B.B LYNGDOH-MLA|02-03| 1 | 1) APPROACH ROAD FROM MAIN | 50,000| 50,000|MEMO NO.DEV.35(VII)2/2002/37-A| 25,000| 75 % | 25,000 | |IN PROGRESS
| | | | | ROAD (PWD) LAITKYRHONG VILLAGE| | | | | | | |
| | | | | TO LUMSOHPHIE (THROUGH LOCAL | | | | | | | |
| | | | | COMMITTEE LAITKYRHONG VILLAGE | | | | | | | |
| BDO | S.S LYNGDOH-MLA|02-03| 4 | 1) CONST. OF FOOTPATH AT | 50,000| 2,28,571|MEMO NO.DEV.35(VII)2/2002/38-A| 50,000|100 % |NIL |COMPLETED |
| MAWRYNGKNENG | | | | LUMDIENGSAI | | |DT. 18-11-02 | | | | |
| | | | | 2) CONST. OF FOOTPATH AT | 1,00,000| |- DO - | 1,00,000|100 % |NIL |COMPLETED |
| | | | | NONGHALI | | | | | | | |
| | | | | 3) CONST. OF FOOTPATH AT | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | TYNRING | | | | | | | |
| | | | | 4) CONST. OF FOOTPATH AT | 28,571| |- DO - | 28,571|100 % |NIL |COMPLETED |
| | | | | KSEH PONGDENG | | | | | | | |
| BDO | M.N MUKHIM-MLA |02-03| 3 | 1) IMPROVEMENT OF UMSAW | 30,000| 1,20,000|MEMO NO.DEV.35(VII)2/2002-38-A| 30,000|100 % |NIL |COMPLETED |
| MAWRYNGKNENG | | | | RYNGKON ROAD AT UMSAWLUM | | | | | | | |
| | | | | 2) IMPROVEMENT OF FOOTBRIDGE | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | OVER UMNGOT RIVER AT THADAN | | | | | | | |
| | | | | 3) IMPROVEMENT OF VILLAGE ROAD| 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | AT MADAN LANGNING | | | | | | | |
| BDO | E.R KHARKONGOR |02-03| 9 | 1) CONST. OF FOOTPATH AT | 25,000| 2,00,000|MEMO NO.DEV.35(VII)2/2002-38-A| 25,000|100 % |NIL |COMPLETED |
| MAWRYNGKNENG | | | | MAWLYNGAD | | | | | | | |
| | | | | 2) CONST. OF FOOTPATH AT | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | PEPBAH | | | | | | | |
| | | | | 3) CONST. OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | MAWMLUH SMIT | | | | | | | |
| | | | | 4) CONST. OF FOOTPATH AT | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | NONGMADAN, SMIT | | | | | | | |
| | | | | 5) CONST. OF FOOTPATH AT | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | WAHJASYIEM | | | | | | | |
| | | | | 6) CONST. OF FOOTPATH AT | 20,000| |- DO - | 10,000| 40 % | 10,000 | |WORK IN PROGRESS
| | | | | UMTNGAW | | | | | | | |
| | | | | 7) CONST. OF FOOTPATH AT | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | MAWLYNREI, NONGKREM | | | | | | | |
| | | | | 8) CONST. OF FOOTPATH AT | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | SAITDNGIEM | | | | | | | |
| | | | | 9) CONST. OF FOOTPATH AT | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | MAWPYNTHAW, NONGKREM | | | | | | | |
| BDO MAWSYNRAM | J.A LYNGDOH-MLA|02-03| 1 | 1) EXTENSION OF FOOTPATH TO | 25,000| 25,000|MEMO NO.DEV.35(VII)2/2002/39-A| 25,000|100 % |NIL |COMPLETED |
| | | | | UMKSEH PRESBYTERIAN CHURCH | | |DT. 18-11-02 | | | | |
| BDO MAWSYNRAM | Dr.DONKUPAR ROY|02-03| 1 | 1) CONST. OF FOOTPATH AT | 40,000| 40,000|MEMO NO.DEV.35(VII)2/2002/39-A| 40,000|100 % |NIL |COMPLETED |
| | MLA | | | NONGTRAI VILLAGE MAWSYNRAM | | |DT. 18-11-02 | | | | |
| BDO MAWSYNRAM | D.P IANGJUH-MLA|02-03| 8 | 1) CONST. OF FOOTPATH FROM | 50,000| 4,28,571|MEMO NO.DEV.35(VII)2/2002/39-A| 50,000|100 % |NIL |COMPLETED |
| | | | | M.D ROAD TO ALPHIRIDA SHANG- | | |DT. 18-11-02 | | | | |
| | | | | PLIANG DONG SOHKLONG MAWSYNRAM| | | | | | | |
| | | | | VILLAGE | | | | | | | |
| | | | | 2) CONST. OF PUBLIC NULLA FROM| 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | BAH DRO COMPOUND TO BAH MEREDY| | | | | | | |
| | | | | COMPOUND DONGSHILLIANG | | | | | | | |
| | | | | 3) CONST. OF FOOTPATH WITHIN | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | TERAJAMRA VILLAGE | | | | | | | |
| | | | | 4) CONST. OF FOOTPATH WITHIN | 50,000| |- DO - | | | | |
| | | | | PEPPARA VILLAGE | | | | | | | |
| | | | | 5) CONST. OF FOOTPATH FROM | 38,571| |- DO - | 38,571|100 % |NIL |COMPLETED |
| | | | | M.B ROAD TO HOLLAND COMPOUND | | | | | | | |
| | | | | MAWSYNRAM VILLAGE | | | | | | | |
| | | | | 6) CONST. OF FOOTPATH WITHIN | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | DOMSKONG VILLAGE | | | | | | | |
| | | | | 7) CONST. OF FOOTPATH WITHIN | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | PYNDENDAKHI VILLAGE | | | | | | | |
| | | | | 8) CONST. OF FOOTBRIDGDE AT | 90,000| |- DO - | 90,000|100 % |NIL |COMPLETED |
| | | | | PHODSDEI KENMYNSAW VILLAGE | | | | | | | |
| BDO MAWSYNRAM | B.B NONGSIEJ |02-03| 3 | 1) CONST. OF CEMENT FOOTPATH | 25,000| 58,571|MEMO NO.DEV.35(VII)2/2002/54-A| 25,000|100 % |NIL |COMPLETED |
| | MLA | | | FROM PWD ROAD TO CATHOLIC | | |DT. 19-12-02 | | | | |
| | | | | GRAVEYARD KMAWANRUM | | | | | | | |
| | | | | 2) CONST. OF CEMENT FOOTPATH | 20,000| |- DO - | 20,000|100 % |NIL |COMPLETED |
| | | | | FROM PWD ROAD TO WEILOI | | | | | | | |
| | | | | PRESBYTERIAN L.P SCHOOL | | | | | | | |
| | | | | 3) CONST. OF CEMENT FOOTPATH | 13,571| |- DO - | 13,571|100 % |NIL |COMPLETED |
| | | | | WITHIN PHODJAUD AT WAHMAWPAT | | | | | | | |
| BDO PYNURSLA | B.B LYNGDOH-MLA|02-03| 6 | 1) APPROACH ROAD FROM PWD ROAD| 25,000| 2,03,571|MEMO NO.DEV.35(VII)2/2002/40-A| 25,000|100 % |NIL |COMPLETED |
| | | | | (TURNING POINT) PYNTER TO THE | | |DT. 18-11-02 | | | | |
| | | | | INTERIOR PART OF THE VILLAGE | | | | | | | |
| | | | | PYNTER | | | | | | | |
| | | | | 2) APPROACH ROAD FROM PWD ROAD| 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | TO L.P SCHOOL NONGSDER P.O | | | | | | | |
| | | | | PYNURSLA | | | | | | | |
| | | | | 3) APPROACH ROAD FROM PWD ROAD| 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | TO PRESBYTERIAN CHURCH MAWPRAN| | | | | | | |
| | | | | NONGLYNDING MAWPRAN | | | | | | | |
| | | | | 4) APPROACH ROAD FROM LYNGKYR-| 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | DEM IEWDUH TO NONGLUM LOCALITY| | | | | | | |
| | | | | LYNGKYRDEM (VILL)(THROUGH | | | | | | | |
| | | | | SORDAR RAID LYNGKYRDEM | | | | | | | |
| | | | | 5) APPROACH ROAD FROM PWD ROAD| 78,571| |- DO - | 78,571|100 % |NIL |COMPLETED |
| | | | | TO IEW RAID SHABONG WAHPATHAW | | | | | | | |
| | | | | PYNURSLA (THROUGH THE CHAIRMAN| | | | | | | |
| | | | | IEW WAHPATHAW, PYNURSLA | | | | | | | |
| | | | | 6) APROACH ROAD FROM N.H TO | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | WAHSKONG SIATBAKON (VILL) P.O| | | | | | | |
| | | | | PYNURSLA | | | | | | | |
| BDO PYNURSLA | K.K DKHAR-MLA |02-03| 10 | 1) COMPLETION OF REMAINING | 20,000| 4,28,571|MEMO NO.DEV.35(VII)2/2002/40-A| 20,000|100 % |NIL |COMPLETED |
| | | | | PORTION OF FOOTPATH OF IARBI- | | |DT. 18-11-02 | | | | |
| | | | | NIAW, UMNIUH TMAR | | | | | | | |
| | | | | 2) IMPROVEMENT OF FOOTPATH | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | TOWARDS CATHOLIC GRAVEYARD | | | | | | | |
| | | | | NEAR LAPALANG VILLAGE | | | | | | | |
| | | | | 3) CONST. OF A FOOTBRIDGE OVER| 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | A STREAM AT NONGSOHPHAN VILL. | | | | | | | |
| | | | | 4) CONST. OF A FOOTPATH FROM | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | PWD ROAD TO MAWBYRNE VILLAGE | | | | | | | |
| | | | | 5) CONST. OF FOOTBRIDGE OVER | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | WAH SOHPURA NEAR NONGTYNGUR | | | | | | | |
| | | | | VILLAGE | | | | | | | |
| | | | | 6) REPAIR OF THREE EXISTING | 60,000| |- DO - | 60,000|100 % |NIL |COMPLETED |
| | | | | BRIDGES AT PYRNAI VILLAGE | | | | | | | |
| | | | | 7) EXTENSION OF A FOOTPATH AT | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | MAWSHUN VILLAGE FROM PHYLLAW | | | | | | | |
| | | | | KHONGKLIAM TOWARDS M.E SCHOOL | | | | | | | |
| | | | | 8) CONST. OF FOOTPATH AT | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | LYNGKHONG VILLAGE NEAR | | | | | | | |
| | | | | LYNGKHAT | | | | | | | |
| | | | | 9) COMPLETION OF A FOOTBRIDGE | 80,000| |- DO - | 80,000|100 % |NIL |COMPLETED |
| | | | | AT WEIPASKUR NEAR MAWSHUN | | | | | | | |
| | | | | VILLAGE | | | | | | | |
| | | | | 10) REPAIR OF A FOOTPATH AT | 28,571| |- DO - | 28,571|100 % |NIL |COMPLETED |
| | | | | WAHUMLEIN VILLAGE | | | | | | | |
| BDO 12-SHNONG | B.B LYNGDOH-MLA|02-03| 5 | 1) MAINTENANCE OF APPROACH | 25,000| 1,75,000|MEMO NO.DEV.35(VII)2/2002/41-A| 25,000|100 % |NIL |COMPLETED |
| | | | | ROAD FROM MAIN ROAD TO THE | | |DT. 18-11-02 | | | | |
| | | | | RESIDENCE OF BAH SYRLOK DKHAR | | | | | | | |
| | | | | AT IEWMAWIONG P.O LAITLYNGKOT | | | | | | | |
| | | | | 2) MAINTENANCE OF MOTORABLE | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | ROAD FROM IEWMAWIONG TO | | | | | | | |
| | | | | NONGTHYMMAI UMTHLI(THROUGH | | | | | | | |
| | | | | RANGBAH SHNONG NONGTHYMMAI | | | | | | | |
| | | | | UMTHLI) | | | | | | | |
| | | | | 3) MAINTENANCE OF MOTORABLE | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | ROAD FROM UMTHLI MAIN ROAD TO | | | | | | | |
| | | | | KTIEHBANIA UMTHLI P.O | | | | | | | |
| | | | | LAITLYNGKOT | | | | | | | |
| | | | | 4) COMPLETION OF APPROACH ROAD| 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | FROM PWD ROAD NEAR BAH PURSHON| | | | | | | |
| | | | | RESIDENCE TO MADAN LYNGDOH | | | | | | | |
| | | | | RAID NONGKYNRIH | | | | | | | |
| | | | | 5) APPROACH ROAD FROM LAITMAW-| 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | ROH VILLAGE TO SYLLAIMON | | | | | | | |
| | | | | VILLAGE P.O LAITLYNGKOT | | | | | | | |
| BDO 12-SHNONG | F.A KHONGLAM |02-03| 19 | CONSTRUCTION OF FOOTPATH AT :-| | | | | | | |
| | MLA | | | 1) THANGKYRTA KHADARSHNONG | 10,000| 2,18,571|MEMO NO.DEV.35(VII)2/2002/60-A| 10,000|100 % |NIL |COMPLETED |
| | | | | | | |DT. 6-1-03 | | | | |
| | | | | 2) MAWKDOK | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 3) MAWJRONG | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 4) KHADARSHNONG | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 5) KHROH IAWHIAR KHADARSHNONG | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 6) DEWLIEH | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 7) SWER SHILIANGWAH | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 8) KONGTHONG | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 9) MAWBEH | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 10) SOHRARIM | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 11) SHNONGPDEI VILLAGE | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 12) DIENGSONG | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 13) SUKTIA | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 14) WAHBAH | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 15) NONGTRAW | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 16) DYMPEP | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 17) DEWIONG | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 18) SYNRANG SOHNOH | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 19) NONGTHYMMAI | 8,571| |- DO - | 8,571|100 % |NIL |COMPLETED |
| BDO SHELLA- | DONKUPAR ROY |02-03| 12 | IMPROVEMENT, ETC. OF SHELLA | | | | | | | |
| BHOLAGANJ | MLA | | | VILLAGE ROAD AT THE FOLLOWING | | | | | | | |
| | | | | PORTIONS :- | | | | | | | |
| | | | | 1) PORTIONS NO.1-IMPROVEMENT | 25,000| 3,88,571|MEMO NO.DEV.35(VII)2/2002/42-A| 25,000|100 % |NIL |COMPLETED |
| | | | | OF GRADIANT ETC. | | |DT. 18-11-02 | | | | |
| | | | | 2) PORTION NO.1-WIDENING AND | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | WALLING ETC. | | | | | | | |
| | | | | 3) PORTION NO.3-WIDENING,ETC. | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | 4) PORTION NO.4-WIDENING ETC. | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | 5) PORTION NO.5-WIDENING ETC. | 25,000| |- DO - | 25,000|100 % |NIL |COMPLETED |
| | | | | 6) PORTION NO.6-CONST. OF | 50,000| |- DO - | 50,000|100 % |NIL |COMPLETED |
| | | | | STATION OR WIDENING INTO | | | | | | | |
| | | | | DOUBLE LANE | | | | | | | |
| | | | | 7) CONST. OF FOOTPATH AT RC | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | SOHBAR SHELLA | | | | | | | |
| | | | | 8) CONST. OF FOOTBRIDGE AT | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | UMIONG (MAWTHANG) SHELLA | | | | | | | |
| | | | | 9) CONST. OF FOOTPATH FROM | 40,000| |- DO - | 40,000|100 % |NIL |COMPLETED |
| | | | | BYRONG PRES. CHURCH TO PLAY | | | | | | | |
| | | | | GROUND BYRONG, SHELLA | | | | | | | |
| | | | | 10) CONST. OF FOOTPATH AT | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | NONGNENG (SHELLA) | | | | | | | |
| | | | | 11) CONST. OF FOOTPATH AT | 30,000| |- DO - | 30,000|100 % |NIL |COMPLETED |
| | | | | THANGKHARANG PRES. CHURCH, | | | | | | | |
| | | | | THANGKHARANG SHELLA | | | | | | | |
| | | | | 12) CONST. OF FOOTPATH TO THE | 28,571| |- DO - | 28,571|100 % |NIL |COMPLETED |
| | | | | RESIDENCE OF SHRI ODAL KSANING| | | | | | | |
| | | | | UMDOH, SHELLA | | | | | | | |
| BDO SHELLA | F.A KHONGLAM |02-03| 17 | CONSTRUCTION OF FOOTPATH AT :-| | | | | | | |
| BHOLAGANJ | MLA | | | 1) KHLIEHSHNONG, SOHRA | 15,000| 2,10,000|MEMO NO.DEV.35(VII)2/2002/61 | 15,000|100 % |NIL |COMPLETED |
| | | | | | | |DT. 6-1-02 | | | | |
| | | | | 2) SOHRA, MAWSMAI | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 3) SAITSOHPEN, SOHRA | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 4) MARAIKAPHON, SOHRA | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 5) R.K MISSION SCHOOL RYNGUD | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 6) POMSOHMEN, SOHRA | 15,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 7) MAWSMAI, SOHRA | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 8) NONGPRIANG, SOHRA | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 9) MAWMIHTHIED | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 10) MAWKISYIEM | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 11) WAHUTIM | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 12) MAWSIANGEI | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |
| | | | | 13) LAITIAM VILLAGE | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 14) RNGI MAWSAW | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 15) KEMRANG | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 16) RYNGUD | 15,000| |- DO - | 15,000|100 % |NIL |COMPLETED |
| | | | | 17) SOHKYNDUH | 10,000| |- DO - | 10,000|100 % |NIL |COMPLETED |